top of page

Sourcing Schedule

Sourcing Schedule: PureCotton Medical follows a detailed sourcing and production schedule to ensure all garments are developed, manufactured, and delivered on time. The timeline for each product includes clear deadlines for every stage of the production process, from concept initiation to floor placement.

Each stage follows a structured timeline to maintain an efficient workflow. After the initial concept, design is finalized within 60 days, followed by vendor selection 45 days later. Textile and trimming procurement take an additional 60 days post-vendor confirmation. The cut and sew process begins shortly after materials are secured, and completed products are then imported, processed through customs within 7 days, distributed within 10 days, and finally delivered to retail floors within 10 days of reaching the distribution center.

This sourcing and scheduling strategy ensures that PureCotton Medical garments meet launch deadlines while maintaining premium quality standards.

Click to view sourcing schedule

Contact Me!

taylor.hill345@icloud.com

​​​

​

​

©2024 by Taylor Hill Professional Portfolio. Proudly created with Wix.com

  • LinkedIn
bottom of page